摘    要:介绍了侯村变电站 5 0 0kV主接线的特点及其在电网中的作用。回顾了变电站一期完工时主接线的不足之处 ,并对二期神侯Ⅱ回线建成后运行方式的改善进行了分析 ,展望了侯侯线 (侯村———侯马 )建成后的运行情况。

关 键 词:主接线  500kV变电站  电网规划
文章编号:1005-6548(2001)03-0223-03
修稿时间:2001-03-05

The Analysis of Running Reliability of The Main Wire of 500kV after the Second and the Third Expansion of Houcun Substation
SHI Fang . The Analysis of Running Reliability of The Main Wire of 500kV after the Second and the Third Expansion of Houcun Substation[J]. Journal of Electric Power, 2001, 16(3): 223-225
Authors:SHI Fang
Affiliation:SHI Fang 1,
Abstract:The characteristics of breaker and a half scheme in 500kV Houcun substation and the effect in 500kV power grid is introduced.Considering the shortages of the main wire in the first stage,an analysis is made on improvement of the running way when the second transmission line was finished between ShenTou to Houcun ,a prospect of the running situation is made when the transmission line(Houma to Houcun)will be done.
Keywords:main wire  500kV substation  power network programming