核电站安注罐安装就位方案论证
引用本文:郭俊营,赵振东,李忠诚.核电站安注罐安装就位方案论证[J].山西建筑,2009,35(21):160-162.
作者姓名:郭俊营  赵振东  李忠诚
作者单位:深圳中广核工程设计有限公司,广东深圳,518057
摘    要:对某核电站安注罐延迟交货而无法预先安装就位的问题,从核级设备基础所在转换层厚板上预留孔的选取及对运输路径、运输时间的影响进行了分析论证,最终确定了就位方案。

关 键 词:厂房  安注罐  运输  安装就位  方案论证

Installed in place scheme discussion for injection can in nuclear station
GUO Jun-ying,ZHAO Zhen-dong,LI Zhong-cheng.Installed in place scheme discussion for injection can in nuclear station[J].Shanxi Architecture,2009,35(21):160-162.
Authors:GUO Jun-ying  ZHAO Zhen-dong  LI Zhong-cheng
Affiliation:GUO Jun-ying ZHAO Zhen-dong LI Zhong-cheng
Abstract:Aiming at the problem that the injection can could not be installed in time caused by the delay of delivery, the paper analyzes from aspects of choosing of the prepared hole on thick board of transferring layer on which the nuclear grade equipment base stay, effects of trans- portation way as well as transportation time, it finally make sure the installation scheme.
Keywords:working house  injection can  transportation  installed in place  scheme discussion