双侧壁导坑中洞法开挖地表沉降规律分析
引用本文:熊炎林.双侧壁导坑中洞法开挖地表沉降规律分析[J].山西建筑,2010,36(15):313-315.
作者姓名:熊炎林
作者单位:中铁隧道集团科研所,河南,洛阳,471009
摘    要:以广州地铁五号线东端站厅通道施工为例,对双侧壁导坑中洞法施工做出简要介绍,并对施工过程中对地表的横向和纵向变形情况做分析,得到双侧壁导坑法施工对地表的影响规律,以期为以后的类似工程提供指导。

关 键 词:双联拱侧壁导坑法  横向沉降槽  纵向沉降槽  封闭成环

On analysis of settlement laws for excavation surface with central hole method of two side-wall pilot tunnel
XIONG Yan-lin.On analysis of settlement laws for excavation surface with central hole method of two side-wall pilot tunnel[J].Shanxi Architecture,2010,36(15):313-315.
Authors:XIONG Yan-lin
Affiliation:XIONG Yan-lin
Abstract:Taking the pavement construction of east station hall in fifth line of Guangzhou subway as an example,the paper introduces the central hole method of two side-wall pilot tunnel,analyzes the horizontal and vertical deformations of the surface in the construction process,and concludes the two side-wall pilot tunnel's influential law on the surface,so as to provide the direction for similar projects.
Keywords:central hole method of two side-wall pilot tunnel  horizontal settlement tank  vertical settlement tank  enclosed ring  