首页 | 本学科首页   官方微博 | 高级检索  
     

五强溪水电站施工导流
引用本文:彭少军.五强溪水电站施工导流[J].水力发电,1994(11):48-51.
作者姓名:彭少军
作者单位:中国水利水电第八工程局
摘    要:五强溪水电站原定采用先围右岸的三期导流方案。后因第二期推迟,经优化改为二期导流方案。第一期过水围堰挡水流量16000m^3/s,水下施工采用预制混凝土组全模板和大型钢模,一期通航由束窄后的左侧主河槽通航;第二期围堰挡水18000m^3/s,上游采用碾压混凝土围堰净化工作日60d,下游采用粘土心墙土石过水围堰,溢流面采用宽台阶式护面,二期通航由设置中孔坝段的临时船闸通航。

关 键 词:五强溪水电站  施工导流  围堰  通航

River Diversion During Construction of Wuqianxi Hydropower Station
Peng Shaojun.River Diversion During Construction of Wuqianxi Hydropower Station[J].Water Power,1994(11):48-51.
Authors:Peng Shaojun
Affiliation:The Eighth Construction Bureau of Water Resources and Hydropower
Abstract:In Wuqiangxi Hydropower Station, the original river diversion scheme was a three--staged diversion starting from the right bank . Because of postponement of project commencement, the scheme was revised into two-staged diversion through optimal design. The first--stagecofferdam was designed to hold a flow discharge of 16000m3/s. Subaqueous construction was carried out through precast concrete mould plates and large-sized steel mould plates. In the first stage, the left-hand side of the narrowed mainstream was used for navigation. The second--stage cofferdams was design to hold 18000m3/s discharge. its upstream cofferdam was a roller compacted concrete dam, while its downstream cofferdam was earth-rock overtopped cofferdam with clay core. the overflow surface was wide step facing. In the second stage, a temporary ship lock was built in the middle dam section for navigation.
Keywords:Wuqiangxi hydropower Station  river diversion during construction  general progress of construction  cofferdam  navigation
本文献已被 CNKI 维普 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号