五强溪水电站施工导流
引用本文:彭少军. 五强溪水电站施工导流[J]. 水力发电, 1994, 0(11): 48-51
作者姓名:彭少军
作者单位:中国水利水电第八工程局
摘    要:五强溪水电站原定采用先围右岸的三期导流方案。后因第二期推迟,经优化改为二期导流方案。第一期过水围堰挡水流量16000m^3/s,水下施工采用预制混凝土组全模板和大型钢模,一期通航由束窄后的左侧主河槽通航;第二期围堰挡水18000m^3/s,上游采用碾压混凝土围堰净化工作日60d,下游采用粘土心墙土石过水围堰,溢流面采用宽台阶式护面,二期通航由设置中孔坝段的临时船闸通航。

关 键 词:五强溪水电站 施工导流 围堰 通航

River Diversion During Construction of Wuqianxi Hydropower Station
Peng Shaojun. River Diversion During Construction of Wuqianxi Hydropower Station[J]. Water Power, 1994, 0(11): 48-51
Authors:Peng Shaojun
Affiliation:The Eighth Construction Bureau of Water Resources and Hydropower
Abstract:In Wuqiangxi Hydropower Station, the original river diversion scheme was a three--staged diversion starting from the right bank . Because of postponement of project commencement, the scheme was revised into two-staged diversion through optimal design. The first--stagecofferdam was designed to hold a flow discharge of 16000m3/s. Subaqueous construction was carried out through precast concrete mould plates and large-sized steel mould plates. In the first stage, the left-hand side of the narrowed mainstream was used for navigation. The second--stage cofferdams was design to hold 18000m3/s discharge. its upstream cofferdam was a roller compacted concrete dam, while its downstream cofferdam was earth-rock overtopped cofferdam with clay core. the overflow surface was wide step facing. In the second stage, a temporary ship lock was built in the middle dam section for navigation.
Keywords:Wuqiangxi hydropower Station   river diversion during construction   general progress of construction   cofferdam  navigation