刘家峡水电站尾水位抬高的原因及清渣后效益分析
引用本文:李贵生,樊建才,魏同新.刘家峡水电站尾水位抬高的原因及清渣后效益分析[J].西北水电,2003(4):65-67.
作者姓名:李贵生  樊建才  魏同新
作者单位:刘家峡水电厂,甘肃永靖,731600
摘    要:刘家峡水电站尾水河床,在电站施工期及运行初期因各种因素影响,造成河床内堆渣、冲坑交替发生,局部河段河底高程已抬高了10m,水下地形已稳定。若采取措施,在局部河段清渣,尾水位高程降低,发电量增加,经济效益十分可观。

关 键 词:刘家峡水电站  装机容量  增容改造  尾水堆渣  清渣
文章编号:1006-2610(2003)04-0065-03
修稿时间:2002年10月6日

Analysis on origins of tailwater level increase and benefit of Liujiaxia hydropower station after tailrace debris removal
LI Gui-sheng,FAN Jian-cai,WEI Tong-xin.Analysis on origins of tailwater level increase and benefit of Liujiaxia hydropower station after tailrace debris removal[J].Northwest Water Power,2003(4):65-67.
Authors:LI Gui-sheng  FAN Jian-cai  WEI Tong-xin
Abstract:Due to various origins during construction and operation debris deposition and scouring pit occur alternatively in the tailrace channel of the Liujiaxia hydropower station. The local riverbed has raised by 10 m and the bottom profile is stabilized. If measures are adopted to remove the debris deposited in the riverbed and reduce the tailwater level, the economic benefit is considerable by increasing power generation.
Keywords:tailrace debris  origin analysis  debris removal  electricity benefit