鞍钢第三炼钢厂2号板坯连铸机仪表检测与控制
引用本文:张刚,郭放.鞍钢第三炼钢厂2号板坯连铸机仪表检测与控制[J].鞍钢技术,2002(4):30-32.
作者姓名:张刚  郭放
作者单位:鞍钢集团新钢铁公司第三炼钢厂 (张刚),鞍钢集团设备检修协力中心(郭放)
摘    要:论述了鞍钢第三炼钢厂2号连铸机自动化仪表控制系统的构成,并对板坯连铸机仪表检测和控制功能进行详细的介绍.

关 键 词:连铸机  仪表  检测  控制
修稿时间:2002年1月7日

Detection and Control Equipment for No.2 Slab Continuous Caster in Angang No.3 Steelmaking Plant
Zhang Gang.Detection and Control Equipment for No.2 Slab Continuous Caster in Angang No.3 Steelmaking Plant[J].Aisc Techniques,2002(4):30-32.
Authors:Zhang Gang
Affiliation:Zhang Gang (The No.3 Steelmaking Plant of Angang New Iron and Steel Co.) Guo Fang (Angang Equipment Repair Service Center)
Abstract:The constitute of the automatic instrument control system for the No.2 slab continuous caster in Angang No.3 Steelmaking Plant is described. The detection process and the control function of the instrument for the slab continuous caster are also introduced in detail.
Keywords:continuous cater  instrument  detection  control