首页 | 本学科首页   官方微博 | 高级检索  
     

东北电网调峰填谷的新思路
引用本文:沈磊,徐珍懋.东北电网调峰填谷的新思路[J].水力发电,1994(12):35-36,14.
作者姓名:沈磊  徐珍懋
作者单位:东北电管局
摘    要:目前东北电网尖峰电力不足,低谷容量闲置,而正在申请立项的大型抽水蓄能电站在2000年以前难以投产。为此提出采用在梯级水电厂上扩建泵站或抽水蓄能机组的办法,并具体研究了建设白山泵站的可行性,认为这是一条投产,见效快的好路子。

关 键 词:东北地区  电力网  调峰填谷  载荷  扩建

New Thought in Regulating System Load of the Northeast Power Network
Shen Lei, Xu Zhenmao.New Thought in Regulating System Load of the Northeast Power Network[J].Water Power,1994(12):35-36,14.
Authors:Shen Lei  Xu Zhenmao
Affiliation:Northeast Bureau of Electric of Electric Power
Abstract:At present, there is insufficient power supply at peak load, while surplus power generating capacity at trough load. The planned pumped storage hydroplants can not be put into operation before the year 2000.Thus, it is suggested that pump stations or pumped storage generating units be installed at the existing cascade hydropower stations. The feasibility of Baishan pump station was studied. It is believed that this is less investment and more effective measure.
Keywords:the Notrtheast Power Network  regulating peak and trough load  extension  load