梨园水电站4号引水道下弯段塌方的处理措施
引用本文:陈剑. 梨园水电站4号引水道下弯段塌方的处理措施[J]. 西北水电, 2013, 0(6): 47-49
作者姓名:陈剑
作者单位:中国水利水电建设工程咨询西北公司,西安710075
摘    要:通过对梨园水电站4号引水道下弯段塌方原因分析,针对塌方情况,采用混凝土回填塌方空腔、待凝、二次开挖、支护、预应力锚索加强支护等有效措施进行处理,取得了良好的效果。

关 键 词:引水道  塌方  处理方法  梨园水电站

Treatment Measures for Collapse of Lower Curve Section of Penstock 4, Liyuan Hydropower Station
CHEN Jian. Treatment Measures for Collapse of Lower Curve Section of Penstock 4, Liyuan Hydropower Station[J]. Northwest Water Power, 2013, 0(6): 47-49
Authors:CHEN Jian
Affiliation:CHEN Jian (China Hydro Consulting Engineering Corporation, Northwest Branch, Xi'an 710075 ,China)
Abstract:Through analysis on causes of collapse of lower curve section of Penstock 4, Liyuan Hydropower Station, effective measures such as concrete backfilling of the collapse cavity, concrete setting, a second excavation, support and strengthening support with pres- tressed anchor cable, ere are applied for treatment of the collapse. And an expected result is achieved accordingly.
Keywords:penstock  collapse  treatment method  Liyuan Hydropower Station