Exact methods for the resource levelling problem |
| |
Authors: | Thorsten Gather Jürgen Zimmermann Jan-Hendrik Bartels |
| |
Affiliation: | 1.Institute of Management and Economics,Clausthal University of Technology,Clausthal-Zellerfeld,Germany |
| |
Abstract: | We present a project scheduling problem subject to general temporal constraints where the utilization of a set of renewable
resources has to be smoothed over time. For solving the NP-hard optimization problem, we point out some important structural
properties and introduce a new enumeration scheme. Combining this enumeration scheme with some branch-and-bound techniques,
we propose an appropriate solution procedure for the project scheduling problem at hand. To outline the practical importance
of resource levelling, we sketch exemplary the optimization of mid-term planning schedules with regard to the resource requirements
of IT projects. Finally, we present results from a comprehensive computational study on problem instances of the well-known
rlp_j10 and rlp_j20 test sets devised by Kolisch et al. (Benchmark Instances for Project Scheduling Problems, Kluwer, Boston, 1999). |
| |