摘    要:鉴于龚嘴水电站运行发电已40多年,溢洪道溢流面未进行过修补,作为常规溢洪道7~9号溢流面冲蚀磨损严重,局部已可见钢筋,介绍了溢洪道溢流面采用NE-Ⅱ型环氧砂浆修补施工技术,包括材料选取、围堰结构和架立、环氧材料修补施工工艺等。

关 键 词:龚嘴水电站  溢流面  NE-Ⅱ型环氧砂浆  施工技术

Construction Techniques for Repairing of Overflow Surfaces in the Spillway of Gongzui Hydropower Station
LU Jiabin.Construction Techniques for Repairing of Overflow Surfaces in the Spillway of Gongzui Hydropower Station[J].Hubei Water Power,2014(3):53-55.
Authors:LU Jiabin
Affiliation:LU Jiabin (The Dam and Reservoir Management Center of Guodian Dadu River Basin Hydropower Development Co. , Ltd. , Leshan 614900, China)
Abstract:Gongzui hydropower station has been operated for more than 40 years. However, the overflow surfaces in its spillway have not been repaired. Actually, the No. 7 - 9 overflow surfaces in the ordinary spillway are of serious erosion and abrasion and reinforcing steel can be seen in some places. Construction procedure adopting the NE-Ⅱ epoxy mortar to repair the overflow surfaces is introduced, including the material selection, cofferdam structure and its erection, con- struction technique of the repairing work with epoxy material, and so on.
Keywords:Gongzui hydropower station  overflow surface  NE-Ⅱ epoxy mortar  construction technique