引进型 300MW 机组给水全程控制系统 |
| |
引用本文: | 盛赛斌. 引进型 300MW 机组给水全程控制系统[J]. 武汉大学学报(工学版), 1997, 0(6) |
| |
作者姓名: | 盛赛斌 |
| |
摘 要: | 阐述了武汉青山电厂改建工程的300MW单元发电机组锅炉给水全程控制系统的特点,该系统控制回路采用美国贝利(Bailey)公司的INFI-90集散控制系统,系统中设计了合理的补偿校正环节及跟踪切换线路,大大改善了系统的调节品质.
|
关 键 词: | 跟踪;给水全程控制;补偿校正 |
Feedwater Full process Control System for Introduced 300MW Generator Set |
| |
Affiliation: | College of Electric Engineering |
| |
Abstract: | This paper focuses on discussion on the feature of feedwater full process control system for boiler of 300MW unit generator set of the reconstruction engineering of Qingshan Power Plant,Wuhan,Hubei.The control loop of this system applied INFI-90 DCS of Bailey co., USA.The reasonable complement correcting link and trace switch cricuit designed in the system improved its adjusting quality greatly. |
| |
Keywords: | tracing feedwater full process control complement correcting |
本文献已被 CNKI 等数据库收录! |