北江大堤石角堤段防渗工程效果分析
引用本文:张挺,曹洪,詹杰民,周红星.北江大堤石角堤段防渗工程效果分析[J].岩石力学与工程学报,2009,28(11):2235-2241.
作者姓名:张挺  曹洪  詹杰民  周红星
作者单位:(1. 中山大学 应用力学与工程系,广东 广州 510275;2. 广东省水利水电科学研究院,广东 广州 510610;;3. 华南理工大学 亚热带建筑科学国家重点实验室,广东 广州 510641)
摘    要: 广东省北江大堤石角堤段为强透水地基,历史上汛期多有险情发生。该堤段采用高喷截渗墙、填砂压渗、反滤排渗体、减压井等工程措施进行防渗加固处理。工程实施后经过多次洪水检验,石角堤段均可安全度汛,未出现严重险情,但也存在一些隐患。通过实测资料分析和渗流场模拟计算,分析各种防渗措施的功效,认为压渗减压工程对本堤段防渗是有效的,并对大堤的防渗安全进行评价,为堤防的防渗建设提供参考。

关 键 词:水利工程堤坝渗流截渗墙压渗减压井
收稿时间:2009-7-1
修稿时间:2009-8-9

EFFECT ANALYSIS OF PREVENTING SEEPAGE ENGINEERING IN SHIJIAO SEGMENT OF NORTH RIVER LEVEE
ZHANG Ting,CAO Hong,ZHAN Jiemin,ZHOU Hongxing.EFFECT ANALYSIS OF PREVENTING SEEPAGE ENGINEERING IN SHIJIAO SEGMENT OF NORTH RIVER LEVEE[J].Chinese Journal of Rock Mechanics and Engineering,2009,28(11):2235-2241.
Authors:ZHANG Ting  CAO Hong  ZHAN Jiemin  ZHOU Hongxing
Affiliation:(1. Department of Applied Mechanics and Engineering,Sun Yat-sen University,Guangzhou,Guangdong 510275,China;;2. Guangdong Research Institute of Water Resources and Hydropower,Guangzhou,Guangdong 510610,China;3. State Key Laboratory of Subtropical Building Science,South China University of Technology,Guangzhou,Guangdong 510641,China);
Abstract:Because the foundation of Shijiao segment of North River Levee is made up of the strong permeable layers, the dangers happened many times during historical flood periods. In order to raising the ability of preventing flood,many reinforcement measures are adopted,including constructing the high pressure-injected cut off walls,counterweight filling,building filtration and drainage structure,relief wells,etc. After the construction,the Shijiao segment stands the tests of floods many times. But the parts of effect of the measurements are arguable. The article is just right about the evaluation of these measurds by analyzing the data of field observations and simulating the seepage field,and a conclusion is drawn that the counterweight filling engineering is effective for this segment. The safety of preventing seepage is appraised. The conclusion is worthy of reference for the designers and managers.
Keywords:hydraulic project  levee  seepage  cut off wall  counterweight filling  relief well