电站锅炉最佳灭火保护动作延时时间的探讨
引用本文:王元强.电站锅炉最佳灭火保护动作延时时间的探讨[J].发电设备,2009,23(6).
作者姓名:王元强
作者单位:广东省粤泷发电有限责任公司,罗定,527217
摘    要:针对电站锅炉炉膛中容易产生爆燃而引发灭火事故,而灭火保护动作延时时间过短又会引发锅炉假灭火停炉事故,因而从理论和实践两方面对锅炉爆燃后炉膛压力的变化进行了探讨,从而恰当地设定灭火保护最佳延时时间,既保证了锅炉的安全运行,又防止了假灭火导致停炉的事故。

关 键 词:电站锅炉  炉膛爆燃  灭火保护  最佳延时时间

Setting of Optimum Delay Time for Flameout Protection of Power Plant Boilers
WANG Yuan-qiang.Setting of Optimum Delay Time for Flameout Protection of Power Plant Boilers[J].Power Equipment,2009,23(6).
Authors:WANG Yuan-qiang
Affiliation:WANG Yuan-qiang(Guangdong Yuelong Power Generation Co.,Ltd.,Luoding 527217,China)
Abstract:Flameout failures resulting from explosive burning in boiler furnace frequently happen in power plants.In order to prevent false flameout failures caused by too short delay time of flameout protection,which may bring about emergency shutdown of the boiler,a study was made,from both theoretical and practical aspects,on the pressure variation in the furnace after deflagration had happened,and hence an optimum delay time obtained,with which safety boiler operation guaranteed and unnecessary boiler shutdown cau...
Keywords:power plant boiler  furnace deflagration  flameout protection  optimum delay time  