大规模充填体下保安矿柱规划及矿体回采顺序研究
引用本文:朱必勇,杨伟,王新民.大规模充填体下保安矿柱规划及矿体回采顺序研究[J].金属矿山,2015,44(7):21-24.
作者姓名:朱必勇  杨伟  王新民
作者单位:1.长沙矿山研究院有限责任公司,湖南 长沙 410012;2.金属矿山安全技术国家重点实验室,湖南 长沙 410012;3.中南大学资源与安全工程学院,湖南 长沙,410083
基金项目:* 国家自然科学基金青年基金项目(编号:51404305)。
摘    要:针对某金属矿长期处于大规模充填体下开采的现状,对-300 m各盘区回采期间的稳定性进行了数值模拟,分析不同方案的采场开采过程中顶板应力、位移等指标的变化规律,并综合分析比较了各方案的回采安全性与经济效益。分析结果表明:将E101采场作为永久性连续盘区时,回采至中期采场顶板处产生1.14 MPa的最大拉应力和75 mm的最大位移;开采后期采场顶板处产生2.30 MPa的最大拉应力和92 mm的最大位移;开采后期采场顶板的抗拉安全系数为1.53;整个顶板岩体稳定性较好,确定将E101作为盘区永久矿柱。根据盘区永久矿柱的位置,提出了4种盘区回采顺序,分析比较不同开采方案的顶板、直接顶板、矿壁及充填体稳定性,确定了从矿体中央连续永久盘区矿柱E101采场向两侧分盘区开采的回采顺序。

关 键 词:充填采矿  盘区矿柱  回采顺序  采场稳定性  数值模拟  

The Permanent Pillar Arrangement and the Stoping Sequence under Large-scale Backfill Body
Zhu Biyong,Yang Wei,Wang Xinmin.The Permanent Pillar Arrangement and the Stoping Sequence under Large-scale Backfill Body[J].Metal Mine,2015,44(7):21-24.
Authors:Zhu Biyong  Yang Wei  Wang Xinmin
Affiliation:1.Changsha Mining Research Institute Co.,Ltd.,Changsha,410012,China;2.State Key Laboratory of Safety Technology of Metal Mines,Changsha 410012,China;3.School of Resources and Safety Engineering,Central South University,Changsha 410083,China
Abstract:Based on the present mining situation that a metallic ore under the large-scale backfill body has been mined for a long period of time,numerical simulation on the stability of the stope during mining process at -300 m of each panel zone was made to analyze the changing rules of the roof stress,displacement and other indicators during mining process and comprehensively compare the recovery safety and economic benefits of each program.The results show that:when E101 stope is considered as a permanent consecutive penal pillar,the maximum tensile stress of 1.14 MPa and maximum displacement of 75 mm are generated at roof in the middle period;the maximum tensile stress of 2.30 MPa and maximum displacement of 92 mm are generated at the end of mining,meanwhile the roof tensile safety factor is 1.53.The entire roof rock stability is good,so E101 panel is determined as the permanent pillar.According to the position of the permanent penal pillar,four panel stoping sequences are proposed.After comparing the roof stability,immediate roof,wall and backfill of different mining plan,the mining sequence from the permanent pillar stopes E101ly extending to two side is determined.
Keywords:Filling mining  Panel pillar  Mining sequence  Stope stability  Numerical simulation