首页 | 本学科首页   官方微博 | 高级检索  
     

新疆夏特水电站水轮机抗磨措施研究
引用本文:张惠忠,陈一平,杨建明,庞嘉扬,华红,曾永忠. 新疆夏特水电站水轮机抗磨措施研究[J]. 水力发电, 2020, 46(4): 70-74
作者姓名:张惠忠  陈一平  杨建明  庞嘉扬  华红  曾永忠
作者单位:中国电建克州新隆能源开发有限公司,新疆喀什845450;西华大学流体及动力机械教育部重点实验室,四川 成都610039
基金项目:国家重点研发专项项目资助(2018YFB0905200);国家自然科学基金项目资助(51279172)。
摘    要:新疆夏特水电站所在克孜河中游含沙量高,是典型的多泥沙河流电站,高含沙量对电站水轮机过流部件的泥沙磨损影响很大。详细分析了电站泥沙的形成及输沙能力以及电站泥沙颗粒级配情况,对夏特电站可采用的水轮机进行了沙水流动的数值模拟和关键过流部件泥沙磨损试验,预估了水轮机的泥沙磨损情况,并提出了抗泥沙磨损的措施。研究结果为夏特水电站水轮机的抗磨设计和运行提供了重要参考依据。

关 键 词:多泥沙河流  水轮机  泥沙磨损  抗磨措施  夏特水电站

Research on Anti-Erosion Measures for Turbines in Xinjiang Xiate Hydropower Station
ZHANG Huizhong,CHEN Yiping,YANG Jianming,PANG Jiayang,HUA Hong,ZENG Yongzhong. Research on Anti-Erosion Measures for Turbines in Xinjiang Xiate Hydropower Station[J]. Water Power, 2020, 46(4): 70-74
Authors:ZHANG Huizhong  CHEN Yiping  YANG Jianming  PANG Jiayang  HUA Hong  ZENG Yongzhong
Affiliation:(PowerChina Kezhouxinlong Energy Development Co.,Ltd.,Kashi 845450,Xinjiang,China;Key Laboratory of Fluid and Power Machinery(Xihua University)of Ministry of Education,Chengdu 610039,Sichuan,China)
Abstract:Xiate Hydropower Station is located at the middle reaches of Kezi River in Xinjiang.The high sediment concentration of Kezi River has a great influence on the erosion of the flow components of turbines.The formation and transport capacity of sediment of the power station,as well as the gradation of sediment particles are analyzed in detail.The sand-water flow of the turbine used in this power station is numerically simulated,and the sediment erosions of key flow components are tested.The sediment erosion of turbine is estimated,and the measures to resist the erosion are also put forward.The results will provide important references for the anti-erosion design and operation of turbines in Xiate Hydropower Station.
Keywords:sediment-laden river  turbine  sediment erosion  anti-erosion measures  Xiate Hydropower Station
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏