首页 | 本学科首页   官方微博 | 高级检索  
     

三峡工程大江深水截流技术研究
引用本文:刘乃义 刘力中. 三峡工程大江深水截流技术研究[J]. 中国三峡建设, 1997, 4(8): 16-18
作者姓名:刘乃义 刘力中
作者单位:长江委长江科学院宜昌科学研究所
摘    要:三峡工程大江截流的规模巨大,综合指标居世界同类工程的前列。在水深,流量,大,工期紧的困难上,确保大江胜利截流,必须做好截流技术研究和相 的实施准备。宜昌科研所运用几个不同比尺及功能的水力学模型研究大江深水截流有关的水力学问题,提出大江截流平势垫底,两岩戗堤提前进占的方案,可以顺利实现截流。

关 键 词:三峡工程 深水截流 戗堤坍塌 立堵法截流

Technology of River Closure in Deep Water
Liu Naiyi and Liu Lizhong. Technology of River Closure in Deep Water[J]. China Three Gorges Construction, 1997, 4(8): 16-18
Authors:Liu Naiyi and Liu Lizhong
Affiliation:Liu Naiyi and Liu Lizhong
Abstract:it is essential for the river closure work of the Three Gorges Project with suchcomprehensive indexes as deep water, large discharge, large dumping quantity within a short timeframe without precedent for the similar works in the world, that researches on the technique ofriver closure and construction preparation should be fully conducted. The river closure can besuccessfully completed by lifting the elevation of the river bed, reducing the water depth byfrontal dumping from boats in advance, and advancing by end --dumping method from eitherbank in advance, based on several scales of hydraulic model experiments done by the YichangScientific Research institute.
Keywords:Three Gorges Project River closure in deep water Collapse of dike end Lifting elevation of river bed by front-dumping method  