邯钢东区3200mm~3高炉无计划停煤操作实践
引用本文:张凤宇,张刚,郭先燊,侯健.邯钢东区3200mm~3高炉无计划停煤操作实践[J].甘肃冶金,2014(3):16-18.
作者姓名:张凤宇  张刚  郭先燊  侯健
作者单位:河北钢铁集团邯钢公司,河北邯郸056015
摘    要:邯钢3200 m3高炉因突发事故无计划停煤长达8 h,通过快速变停煤焦比、合理控制各项参数,协调理论燃烧温度与炉温的关系,避免了炉况与炉温的大幅度波动。

关 键 词:大型高炉  无计划停煤  操作实践

Operating Practice of Unplanned Stopping Coal Injection in Eastern 3200 m3 BF of Handan Iron and Steel Co.Ltd.
ZHANG Feng-yu,ZHANG Gang,GUO Xian-shen,HOU Jian.Operating Practice of Unplanned Stopping Coal Injection in Eastern 3200 m3 BF of Handan Iron and Steel Co.Ltd.[J].Gansu Metallurgy,2014(3):16-18.
Authors:ZHANG Feng-yu  ZHANG Gang  GUO Xian-shen  HOU Jian
Affiliation:( Hangang Co. Ltd. of Hebei Iron and Steel Group, Handan 056015,China)
Abstract:The unplanned stopping coal injection in eastern 3200 m3 BF of Hangang was up to 8 hours,through rapid chan-ging the coke ratio of stopping coal injection , reasonable controlling every parameter , coordinating theoretical combustion temperature and furnace temperature ,avoided the volatility of furnace condition and temperature .
Keywords:large sized blast furnace  unplanned stopping coal injection  operating practice