A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration |
| |
Authors: | Hadi Moradi |
| |
Affiliation: | Department of Industrial Engineering, Sharif University of Technology, Tehran, Iran |
| |
Abstract: | The problem of this paper deals with the multi-mode project scheduling problem under uncertainty of activity duration where only the renewable resources are taken into account and a given deadline has to be met at the cost of recruiting additional resources. A heuristic algorithm is employed to solve this problem, and to maintain the robustness of the baseline schedule, the concept of critical chain project management (CCPM) is applied in which a new definition to resource buffer is considered. A simulation methodology is used to determine the size and location of resource buffers in the schedules in which three different buffer sizes and three different uncertainty levels are considered. Results and analysis of the simulation outcomes illustrate that resource buffers are useful and should be simulated by the CCPM schedules, as they help to decrease the total duration of the project during implementation and meet the deadline of the project with more assurance. |
| |
Keywords: | critical chain project management resource buffer robust scheduling multi-mode project scheduling heuristic algorithm |
|
|