首页 | 本学科首页   官方微博 | 高级检索  
     

锦屏二级水电站引水隧洞TBM开挖方案对岩爆风险影响研究
引用本文:吴世勇,周济芳,陈炳瑞,黄满斌. 锦屏二级水电站引水隧洞TBM开挖方案对岩爆风险影响研究[J]. 岩石力学与工程学报, 2015, 34(4): 728-734
作者姓名:吴世勇  周济芳  陈炳瑞  黄满斌
作者单位:(1. 雅砻江流域水电开发有限公司,四川 成都 610051;2. 中国科学院武汉岩土力学研究所,湖北 武汉 430071;3. 沈阳铁道勘察设计院有限公司,辽宁 沈阳 110013)
基金项目:国家科技支撑计划项目(2011BAZ03221B05);国家自然科学基金委主任基金项目(11355001)
摘    要: 为了提高施工效率,降低现场施工人员和设备的风险,锦屏二级水电站1#、3#引水隧洞采用大断面TBM进行施工。超大埋深TBM全断面施工,对于等级较强的岩爆,仍然可能会给TBM设备带来一定伤害。为此,通过微震实时监测和数值分析等手段,开展了TBM施工速度、导洞施工等TBM开挖方案对岩爆风险的影响研究。结果表明,降低TBM施工速率,有利于降低岩爆发生的风险;导洞施工+TBM联合施工对于极强岩爆风险的防范是十分有利的。研究成果可为TBM安全快速掘进提供重要的参考价值,也将为其他工程提供借鉴,具有重要的工程价值。

关 键 词:深埋长隧洞TBM开挖方案岩爆演化规律

RESEARCH ON EFFECTIONS OF EXCAVATION SCHEMES OF TBM ON RISK OF ROCK BURST OF LONG POWER TUNNELS OF JINPING II HYDROPOWER STATION
WU Shiyong;ZHOU Jifang;CHEN Bingrui;HUANG Manbin. RESEARCH ON EFFECTIONS OF EXCAVATION SCHEMES OF TBM ON RISK OF ROCK BURST OF LONG POWER TUNNELS OF JINPING II HYDROPOWER STATION[J]. Chinese Journal of Rock Mechanics and Engineering, 2015, 34(4): 728-734
Authors:WU Shiyong  ZHOU Jifang  CHEN Bingrui  HUANG Manbin
Affiliation:(1. Yalong River Hydropower Development Company,LTD,Chengdu 610051,China;2. Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,Wuhan 430071,China;3. Shenyang Railway Survey Design Consulting Company Limited,Shenyang 110013,China)
Abstract:To improve efficiency of construction and reduce the risk of site construction personnel and equipment,the 1#,3# diversion tunnel of Jinping II hydropower station adopt large-section TBM for construction. The full-section TBM construction under large buried depth,when encounter strong grade rock burst,it still may bring some damage to TBM equipment. Therefore,through the real time microseismic monitoring and numerical analysis,study the influence of TBM excavation scheme、heading construction on the risk of rock burst. The results show that,lowering the rate of construction,can reduce the risk of rock burst;pilot excavation and TBM joint construction is advantageous to prevent strong grade rock burst. The research results can provide important reference value for the safe and rapid excavation of TBM,will also provide reference for other similar project,it has an important engineering value.
Keywords:deep buried long tunnel  TBM  excavation scheme  rock burst  evolution
本文献已被 CNKI 等数据库收录!
点击此处可从《岩石力学与工程学报》浏览原始摘要信息
点击此处可从《岩石力学与工程学报》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏