Operational experience of on-site transport of spent nuclear fuel in Korea |
| |
Abstract: | AbstractWith the rapid development of the nuclear power programme in Korea, the amount of accumulated spent nuclear fuel has inevitably increased year by year. The spent nuclear fuel is being stored in on-site storage pools at the nuclear power plants. As the current storage capacity for spent nuclear fuel is insufficient, at-reactor storage is being expanded at each site with regard to optimisation of technical and economic factors. On-site transport between neighbouring reactors has been necessary to secure sufficient storage capacity for pressurised water reactor spent nuclear fuel assemblies. A complete on-site transport system has been developed, and so far more than 800 spent nuclear fuel assemblies have been transported using two kinds of transport cask. |
| |