首页 | 本学科首页   官方微博 | 高级检索  
     

滩坑水电站施工导流与度汛
引用本文:光辉. 滩坑水电站施工导流与度汛[J]. 水力发电, 2007, 33(1): 45-47
作者姓名:光辉
作者单位:中国水利水电第十二工程局,浙江,杭州,310004
摘    要:滩坑水电站施工导流过水围堰流量大;流速快。围堰防渗墙施工不留龙口,采用先闭气后截流的施工方案,实现深基坑开挖快速施工。汛期适当提高坝体填筑高程;在坝面高差处设置超径石保护,经多次过流后坝面冲刷较少,为今后面板坝汛期填筑积累了经验。

关 键 词:围堰  防渗墙  导流  度汛  滩坑水电站
文章编号:0559-9342(2007)01-0045-03
修稿时间:2006-05-08

Construction Divevsion and Flood Season for Tankeng Hydropower Station
Guang Hui. Construction Divevsion and Flood Season for Tankeng Hydropower Station[J]. Water Power, 2007, 33(1): 45-47
Authors:Guang Hui
Affiliation:China Water Conservancy and Hydropower Engineering Bureau 12, Hangzhou Zhejiang 310004
Abstract:The construction diversion of the Tankeng Hydropower Station has the characteristics of big discharge and quick flow speed on its overflow cofferdam. The cutoff wall of cofferdam was constructed without river-close mouth. The construction measures of air closure first and then river closure are adopted to realize the quick excavation of deep foundation pit. The crest elevation of the main part of dam filling enhanced properly during flood season period and the protect measures that using excess diameter stones at where relative superiority of surfaee of dam.The surface of dam was less eroded after flowing over the cofferdam many times All these measures provide experience for construetion of facing dam in the future.
Keywords:cofferdam   cutoff wall   diversion   pass-through of flood season   Tankeng Hydropower Station
本文献已被 CNKI 维普 万方数据 等数据库收录!