摘    要:50 0t汽车起重机吊尿素塔顶部 ,30 0t履带起重机吊尿素塔底部。分析了吊装过程受力情况后 ,选择吊装索具为6 0 .5 ,6× 37+ 1钢丝绳 ,三弯六股 ,长 36m。给出了吊装方案及技术要求

关 键 词:尿素合成塔  安装  受力分析

Installing technology of urea synthesis tower in 300kt/a ammonia device
SI Sheng-fang.Installing technology of urea synthesis tower in 300kt/a ammonia device[J].Journal of Chemical Industry & Engineering,2000,21(6):41-45.
Authors:SI Sheng-fang
Affiliation:SI Sheng fang [
Abstract:The top of the tower was lifted by a 500t truck crane, and the bottom was lifted by a 300t caterpillar one. After analyzing the force in lifting, 60.5,6×37+1 rope which was 36m long and curved three times to six stands was chosen as crane rope. The lifting schema and technical requirements were given.