摘    要:泗南江水电站建设期间,业主、设计、监理等参建三方计算机信息管理系统的组建和应用,通过实际应用效果判断,该系统的组建给该工程的信息管理带来一定的影响,提高了信息交流处理的工作效率,有利于信息的传递、交换和处理。

关 键 词:泗南江水电站  工程建设  信息管理  系统
文章编号:1006-2610(2007)02-0074-03
收稿时间:2006-08-01
修稿时间:2006-08-01

On computer information management system during construction of Sinanjiang hydropower station
LEI Hai-sheng. On computer information management system during construction of Sinanjiang hydropower station[J]. Northwest Water Power, 2007, 0(2): 74-76
Authors:LEI Hai-sheng
Affiliation:Yunnan Hengcheng Construction Supervision and Consulting Co. Ltd. , Kunming 650051, China
Abstract:The computer information management system was established and applied by the Employer,the Designer and the Engineer during the construction of Sinanjiang hydropower station.By practical application and effect judgment,the system had acquired certain good results,enhanced working efficiency of information exchange and be in favor of information transfer,exchange and processing.
Keywords:Sinanjiang hydropower station  project construction  information management  system