积石峡混凝土面板堆石坝面板混凝土施工技术
引用本文:潘挺,柴建中,边文章.积石峡混凝土面板堆石坝面板混凝土施工技术[J].水力发电,2011,37(11).
作者姓名:潘挺  柴建中  边文章
作者单位:青海禹天监理咨询有限公司,青海西宁,810008
摘    要:积石峡水电站面板坝混凝土面板浇筑采用了无轨滑模施工工艺和Ⅰ、Ⅱ序跳仓补空的施工方法,一次浇筑到坝顶。面板混凝土浇筑质量好、施工速度快、工效高,质量考核优良率为94.4%;混凝土浇筑面积共35 516 m2,仅产生裂缝71条,裂缝数量较少且宽度较窄。

关 键 词:混凝土面板堆石坝  面板混凝土  施工布置  施工准备  施工工艺  积石峡水电站工程  

Slab Concrete Construction Technologies for Jishixia CFRD
Pan Ting,Chai Jianzhong,Bian Wenzhang.Slab Concrete Construction Technologies for Jishixia CFRD[J].Water Power,2011,37(11).
Authors:Pan Ting  Chai Jianzhong  Bian Wenzhang
Affiliation:Pan Ting,Chai Jianzhong,Bian Wenzhang(Qinghai Yutian Supervision Consulting Co.,Ltd.,Xining 810008,Qinghai,China)
Abstract:The slab concrete pouring of Jishixia CFRD is completed from bottom to top in an entire construction process by using trackless sliding form and two block-divided method.The quality of 94.4% total slab concrete area has a good class or above.The construction is also fast and efficient.The total pouring area is 35 516 m2,and there are only 71 cracks with narrow width.
Keywords:CFRD  slab concrete  construction layout  construction preparation  construction technology  Jishixia Hydropower Station project  