周宁水电站碾压混凝土大坝高温季节施工温控措施
引用本文:周顺田. 周宁水电站碾压混凝土大坝高温季节施工温控措施[J]. 水力发电, 2006, 32(12): 79-81
作者姓名:周顺田
作者单位:闽东水电开发有限公司,福建,周宁,355400
摘    要:周宁水电站碾压混凝土大坝施工是决定工程工期的关键项目之一,对其质量又有严格的要求。为了加速工程进度,在6月~7月的高温季节也要进行碾压混凝土施工。为了保证工程质量,在吸取国内先进经验的基础上,采用了切实可行的温控措施,如埋设冷却水管进行混凝土冷却等,取得了一定效果。

关 键 词:大坝  碾压混凝土  温控措施  周宁水电站
文章编号:0559-9342(2006)12-0079-03
收稿时间:2006-11-10
修稿时间:2006-11-10

Temperature Control during High Temperature Seasons for Zhouning Hydropower Station RCC Dam
Zhou Shuntian. Temperature Control during High Temperature Seasons for Zhouning Hydropower Station RCC Dam[J]. Water Power, 2006, 32(12): 79-81
Authors:Zhou Shuntian
Affiliation:The water electricity of Mindong develops the limited company, Zhouning Fujian 355400
Abstract:The construction of Zhouning Hydraulic Power RCC dam is a key to the construction duration,the quality of which shall be controlled strictly.In order to expedite the progress,RCC construction was carried out during high temperature seasons from June to July.Based on domestic advanced experiences,practical temperature control measures were taken to ensure the construction quality.For example,cooling pipes were embedded to cool the concrete,which proved effective.
Keywords:dam  RCC  temperature control  Zhouning Hydropower Station