首页 | 本学科首页   官方微博 | 高级检索  
     

紫湖水库溢洪道高边坡挡墙加固预应力锚索的施工技术简介
引用本文:王清彬.紫湖水库溢洪道高边坡挡墙加固预应力锚索的施工技术简介[J].广西水利水电,2011(3):45-47.
作者姓名:王清彬
作者单位:福建省水利水电工程局有限公司,福建泉州,362000
摘    要:紫湖水库溢洪道高边坡石砌挡墙墙背地质复杂,坡面有较多的孤石,且局部石砌挡墙有变形不稳等现象,为确保边坡稳定,采用预应力锚索加固.论述了预应力锚索施工钻孔、护孔、清孔、张拉及质量控制技术.

关 键 词:预应力锚索  高边坡挡墙  施工技术  紫湖水库

Pre-stressed anchor cable construction for reinforcement of spillway high bank slope retaining wall of Zihu Reservoir
WANG Qing-bin.Pre-stressed anchor cable construction for reinforcement of spillway high bank slope retaining wall of Zihu Reservoir[J].Gx Water Resources & Hydropower Engineering,2011(3):45-47.
Authors:WANG Qing-bin
Affiliation:WANG Qing-bin(Fujian Water Conservancy and Water Power Engineering Bureau Company Limited,Quanzhou 362000,China)
Abstract:The spillway high bank slope of Zihu Reservoir was designed with a dry masonry stone retaining wall.Geological condition is complicated at wall back.There were considerable boulders on the slope surface,and there existed unstable positions with deformation.So pre-stressed anchor cable is adopted to reinforce the bank slope.An introduction was made on the construction technique,including boring,bore protection,bore cleaning,stretching and quality control.
Keywords:Pre-stressed anchor cable  high bank slope retaining wall  construction technique  Zihu Reservoir