瀑布沟水电站料场开采方案研究
引用本文:李光隆,梁日新. 瀑布沟水电站料场开采方案研究[J]. 水利水电技术, 2011, 42(5): 1
作者姓名:李光隆  梁日新
作者单位:中国人民武装警察部队水电第一总队,广西南宁530028
摘    要:瀑布沟水电站工程规模大,大坝填筑量大、上坝强度高、施工干扰大。本文主要从料场规划、开采方案、质量安全控制措施等进行论述和研究,通过合理规划,精心组织,科学管理,满足高峰期上坝强度要求,保证大坝施工质量,完成工期目标。

关 键 词:砾石心墙   堆石坝   料场规划   级配料   开采方案   爆布沟水电站  
收稿时间:2011-03-11

Study on quarrying scheme for construction of Pubugou Hydropower Station
LI Guanglong,LIANG Rixin. Study on quarrying scheme for construction of Pubugou Hydropower Station[J]. Water Resources and Hydropower Engineering, 2011, 42(5): 1
Authors:LI Guanglong  LIANG Rixin
Affiliation:The No1 General Team of Armed Police Hydropower Troops, Nanning530028, Guangxi, China
Abstract:The project scale of Pubugou Hydropower Station is large,of which the construction amount of the dam filling is large along with high construction intensity and more construction interference.The quarry layout,filling material quarrying scheme,measures of the quality control and construction safety,etc.are discussed and studied herein.Through reasonable planning,perfect organization and scientific management,not only the dam construction intensity is satisfied and the construction quality is ensured,but the...
Keywords:gravel core-wall  rockfill dam  quarry layout  graded material  quarrying scheme  Pubugou Hydropower Station  