观音岩水电站右岸碾压混凝土斜层施工工艺
引用本文:王玮,王朝阳,罗斌.观音岩水电站右岸碾压混凝土斜层施工工艺[J].水利水电技术,2011,42(5):68.
作者姓名:王玮  王朝阳  罗斌
作者单位:中国人民武装警察部队水电第一总队,广西南宁530028
摘    要:本文主要介绍了观音岩水电站右岸碾压混凝土斜层施工工艺、工艺流程及经济性分析,阐述了施工中斜层面上骨料分离及坡脚处骨料集中等问题的处理方法。

关 键 词:观音岩水电站  碾压混凝土  斜层  坡脚处理  经济性  
收稿时间:2011-03-11

Inclined layer construction technology for RCC placement on right bank of Guanyinyan Hydropower Station
WANG Wei,WANG Chaoyang,LUO Bin.Inclined layer construction technology for RCC placement on right bank of Guanyinyan Hydropower Station[J].Water Resources and Hydropower Engineering,2011,42(5):68.
Authors:WANG Wei  WANG Chaoyang  LUO Bin
Affiliation:The No. 1 General Team of Armed Police Hydmpower Tmops, Nanning  530028,Guangxi, China
Abstract:The inclined layer construction technology, pmcess flow and economy of the mller-compacted concrete(RCC) on the right bank of Guanyinyan Hydmpower Station are mainly described herein, and then the treatment methods for the pmblems such as aggregate separation on the surface of the inclined layer and the aggregate concentration at the toe of the slope during the con- struction are explained as well.
Keywords:Guanyinyan Hydmpower Station  mller-compacted concrete  inclined layer  treatment on slope toe  economy  