沈阳崇山路污水截流干渠顶管工程设计
引用本文:黄彦,吴雅洁,范卫东.沈阳崇山路污水截流干渠顶管工程设计[J].中国市政工程,2003(3):43-45.
作者姓名:黄彦  吴雅洁  范卫东
作者单位:沈阳市市政工程设计研究院,沈阳,110015
摘    要:针对截流干渠穿越高架桥桥墩基础的特殊情况,结合沈阳市崇山路污水截流干渠顶管工程实例,就截流干渠顶管穿越高架桥桥墩基础工程的设计要点及技术要求(干渠线位和顶管管材等)进行了详细的阐述,并提出了污水截流干渠顶管穿越高架桥墩基础的方法。

关 键 词:污水截流干渠  玻璃钢夹砂管  高架桥  顶管

Design of Shenyang Chongshan Rd Sewage Intercepting Main Canal Pipe-Jacking Works
Huang Yan Wu Yajie Fan Weidong.Design of Shenyang Chongshan Rd Sewage Intercepting Main Canal Pipe-Jacking Works[J].China Municipal Engineering,2003(3):43-45.
Authors:Huang Yan Wu Yajie Fan Weidong
Abstract:Based on the special conditions in which the intercepting main canal crosses the pier bases of elevated bridge,and with Shenyang Chongshan Rd sewage intercepting main canal pipe-jacking works as an example,detailed introduction is made here on design key points and technical requirements(alignment of main canal and pipes of pipe-jacking etc)of the works of intercepting main canal crossing the pier bases of elevated bridge in pipe-jacking,as well as the method for intercepting main canal crossing the pier bases of elevated bridge in pipe-jacking.
Keywords:sewage intercepting main canal      pipe of glass reinforced plastic with sand inclusion  elevated bridge  pipe-jacking