大型储罐倒装法施工立缝和环缝的组对工艺
引用本文:宗涛,王新.大型储罐倒装法施工立缝和环缝的组对工艺[J].电焊机,2012,42(8):61-62.
作者姓名:宗涛  王新
作者单位:1. 新疆石油建设有限责任公司,新疆 克拉玛依,834000
2. 石油天然气克拉玛依工程质量监督站,新疆 克拉玛依,834000
摘    要:介绍了大型储罐倒装法施工立缝和环缝的组对工艺.倒装法采用先提升上层罐体,再围下层壁板的施工顺序.围下层壁板的同时,组对立缝;立缝焊接完成后组对环缝,且环缝组对不用定位焊.相对于正装法,倒装法施工立缝和环缝的组对效率有较大提高.

关 键 词:大型储罐  倒装法  立缝  环缝

Linning up process of vertical seam and girth seam in upside-down construction technology for large storage tank
ZONG Tao , WANG Xin.Linning up process of vertical seam and girth seam in upside-down construction technology for large storage tank[J].Electric Welding Machine,2012,42(8):61-62.
Authors:ZONG Tao  WANG Xin
Affiliation:1.Xinjiang Petroleum Engineering Construction Co.,Ltd.,Karamay 834000,China;2.Karamay Supervision Station of Oil & Gas Construction Project Quality,Karamay 834000,China)
Abstract:In this paper,the group technology of vertical welding and girth welding on the inversion construction of large storage tank is presented.When the shell is lifted at the level of the shell course height,the new plates are put in place during the construction of large storage tank using jacking method.At the same time of the new plates put in place,vertical seams should be linned up and welded and horizontal seams after then.Positioned welding isn’t used to welding horizontal seams after linning up.The productivity of this process is much higher than that of conventional method.
Keywords:storage tank  jacking method  vertical seam  horizontal seam