首页 | 本学科首页   官方微博 | 高级检索  
     

胶凝砂砾石坝施工质量监控系统开发及应用
引用本文:贾金生,赵春,缪纶,张德全,罗兆坤. 胶凝砂砾石坝施工质量监控系统开发及应用[J]. 中国水利水电科学研究院学报, 2018, 16(1): 1-8
作者姓名:贾金生  赵春  缪纶  张德全  罗兆坤
作者单位:中国水利水电科学研究院, 北京 100038,中国水利水电科学研究院, 北京 100038,中国水利水电科学研究院, 北京 100038,大同市守口堡水库工程建设项目部, 山西 大同 037000,北京普天通达科技有限公司, 北京 100083
基金项目:十二五国家科技支撑计划(2014BAB03B04);国家重点基础研究发展计划(2013CB035906);山西省水利科学技术研究与推广项目(2016XS01)
摘    要:胶结颗粒料坝是本文第一作者于2009年提出的一种环境友好的新坝型,分为胶凝砂砾石坝、胶结堆石坝(包括堆石混凝土坝)和胶结土坝,其强调"宜材适构"和"宜构适材"的筑坝理念,具有安全经济、环境友好、漫顶不溃等优点。与碾压式土石坝、混凝土坝等相比,胶凝砂砾石坝施工有自身特点,控制要素不尽相同。本文提出了胶凝砂砾石坝的碾压质量监控系统的总体架构和功能设计,研发了基于自主组网的超宽带三维定位技术,开发了适用于胶凝砂砾石坝的碾压监控算法和软硬件平台,并用于山西守口堡工程和四川顺江堰工程施工质量监控,实践表明该系统既适合于中小工程,也可应用于大型工程。

关 键 词:胶凝砂砾石坝  施工质量监控系统  超宽带定位  拌和系统  碾压
收稿时间:2017-05-09

Development and application of the CSGR dam construction quality monitoring system
JIA Jinsheng,ZHAO Chun,MIAO Lun,ZHANG Dequan and LUO Zhaokun. Development and application of the CSGR dam construction quality monitoring system[J]. Journal of China Institute of Water Resources and Hydropower Research, 2018, 16(1): 1-8
Authors:JIA Jinsheng  ZHAO Chun  MIAO Lun  ZHANG Dequan  LUO Zhaokun
Affiliation:China Institute of Water Resource and Hydropower Research, Beijing 100038, China,China Institute of Water Resource and Hydropower Research, Beijing 100038, China,China Institute of Water Resource and Hydropower Research, Beijing 100038, China,Datong Shoukoubao Reservoir Project Department, Datong 037000, China and Beijing PutianTongda Technology Co., Ltd., Beijing 100083, China
Abstract:Cemented Material Dam was a new dam type of environment-friendly proposed in 2009. It is divided into three types:cemented sand, gravel androck dam (CSGRD), cemented rock-fill dam (CRD, including rock-filled concrete dam), and cemented soil dam(CSD). In the concept of dam design, it is emphasized that "the dam structure is optimized in order to make better use of local materials" and that "proper materials can be selected for the different parts of the dam in order to realize better function of structures".This new type have the benefit of "safe and economical","environment friendly" and "not fail even overtopping". And there are some important differences between CSGRD and Rolling earth rock-fill dam or RCC dam because of the different control elements. The overall framework and function design of the CSGR Dam Construction Quality Monitoring System according to "Technical guideline for cemented granular material dams" were introduced in this paper."Autonomous networking technology using UWB positioning system" and "Algorithm for rolling monitoring analysis" were also developed for CSGRD. The software and hardware platform was developed and used in Shoukoubao CSGRD and Shunjiangyan CSGRD. It is indicated that this system can be used not only in large projects but also in medium-sized and small projects.
Keywords:CSGRD  construction quality monitoring system  UWB positioning system  mixing system  rolling
本文献已被 CNKI 等数据库收录!
点击此处可从《中国水利水电科学研究院学报》浏览原始摘要信息
点击此处可从《中国水利水电科学研究院学报》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号