三峡左厂房1—5^#坝段基础加固预应力锚索施工
引用本文:任宗社,邓德彬.三峡左厂房1—5^#坝段基础加固预应力锚索施工[J].中国三峡建设,1998(9):7-10.
作者姓名:任宗社  邓德彬
作者单位:[1]三七八联营公司 [2]水电三局基础处理公司
摘    要:三峡左岸厂房1-6#坝段轴线长229.8m,基础开挖后形成近70m的高边坡,由于断裂组合形成倾向下游的不利滑动面。加固处理主要采用3000kN级预应力锚索,共218束,长30-55m,钻孔孔径165,总进尺8445.6m,锚索施工一钢管槽开挖交叉进行,施工后经监测,锚索实际伸长率与理论值吻合罗好,锁定锚固损失在1-3%,满足设计要求。

关 键 词:三峡工程  厂房  预应力锚索  施工  坝基加固

Strengthening Penstocks Foundation with Prestressed Cables
Ren Zongshe and Deng Debin.Strengthening Penstocks Foundation with Prestressed Cables[J].China Three Gorges Construction,1998(9):7-10.
Authors:Ren Zongshe and Deng Debin
Affiliation:Ren Zongshe and Deng Debin
Abstract:The blocks No. 1 ~ 6 of the powerhouse at the left side of the spillwayhas an axial length of 229. 8 m. After excavation, the foundation had 70 m high slopewith adverse slide plane toward the downstream. The high slopes were primarily stengthened with 218 strands, 30 ~ 55 m long and 3 Ooo kN prestessed cables. The hole diameter was 165 mm and the total drill length of 8445. 6 m. The anchorage cables wereinstalled alternately with the excavation of the penstock trenches. The monitoring datahave shown that the construction quality meets the design specificaitons, the real elongation ratio of the cables falling within the range of the design values, and the loss ofanchoring force being within 1 % ~ 3 %.
Keywords:Three Gorges Project Left powerhouse Prestressed cable Construction  