摘    要:为了减少煤矿立井冻结施工中的安全事故,通过对立井冻结实际工程案例的分析总结,采用层析分析法对各风险因素的评价指标进行权重计算,并结合模糊评价法建立风险因素综合评价矩阵,最终依据最大隶属度原则得出立井冻结法施工中存在的高风险指标及一般风险指标,在此基础上,从组织、技术、经济等方面制定出对应的风险预控措施,从而有效控制煤矿立井冻结法施工风险。

关 键 词:立井冻结施工  层次分析法  模糊评价  指标权重  风险分析
收稿时间:2019-03-30
修稿时间:2020-05-11

Research on Construction Risk Management of Mine Shaft Freezing Method Based on AHP-Fuzzy
YANG Guo-liang,SONG Jiao-jiao and ZHANG Zhao-ran. Research on Construction Risk Management of Mine Shaft Freezing Method Based on AHP-Fuzzy[J]. CHINA MINING MAGAZINE, 2020, 29(5)
Authors:YANG Guo-liang  SONG Jiao-jiao  ZHANG Zhao-ran
Affiliation:School of Mechanics and Civil Engineering,China University of Mining and Technology Beijing;China;School of Civil Engineering,North China University of Technology;China,School of Mechanics and Civil Engineering,China University of Mining and Technology Beijing,School of Civil Engineering,North China University of Technology
Abstract:In order to reduce safety accidents in shaft freezing construction of coal mine, taking the coal mine shaft freezing construction project as an example, according to the datas of analysis and summary of the implementation of the project, the weights of each evaluation index of construction risk factors is determined by AHP method, and the fuzzy evaluation method is used to establish a comprehensive evaluation matrix of risk factors. According to the principle of maximum membership degree, the high-risk indicators and general risk indicators in the construction of the shaft freezing method are determined. Based on analyzing results, the risk pre-control measures are formulated from the aspects of organization, technology and economy to effectively control the construction risk of the mine shaft freezing method.
Keywords:shaft freezing construction   analytic hierarchy process  fuzzy evaluation  index weights  risk analysis
本文献已被 CNKI 等数据库收录!
点击此处可从《中国矿业》浏览原始摘要信息
点击此处可从《中国矿业》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号