加强调试管理提高电站基建阶段自动投入率
引用本文:易凡,孙瑞铣,张力,罗小平,俞蓓敏. 加强调试管理提高电站基建阶段自动投入率[J]. 华东电力, 1993, 0(6)
作者姓名:易凡  孙瑞铣  张力  罗小平  俞蓓敏
作者单位:上海电力建设启动调试所,上海电力建设启动调试所,上海电力建设启动调试所,上海电力建设启动调试所,上海电力建设启动调试所
摘    要:以上海吴泾热电厂新建2台300MW火电机组为例,介绍上海电力建设启动调试所热工专业在调试过程中的经验与体会,进而对国内大型火电机组在调试阶段及投产初期热工自动投入率不高的原因进行分析和提出解决措施。

关 键 词:大型机组  热工自动控制  投入率

Improve the Availability of Power Plant''''s I&C At Initial Stage by Enhancement of Commissioning Test Management
Yi Fan,Sun Reixian. Improve the Availability of Power Plant''''s I&C At Initial Stage by Enhancement of Commissioning Test Management[J]. East China Electric Power, 1993, 0(6)
Authors:Yi Fan  Sun Reixian
Affiliation:Yi Fan;Sun Reixian
Abstract:The experience and realization of the start-up test of utility power plant's I&C gained by SEPSTIwith two 300MW units in Wujin Power Plant as example are summarized in this paper. A further analysis onthe cause for Iow I&C availability of large fussil-fired units in this country is carried out and the remedial mea-sures suggested.
Keywords:large power generating unit  instrument and controI (I&C)  availability