首页 | 本学科首页   官方微博 | 高级检索  
     

施工期钻井井壁混凝土应变实测分析
引用本文:杨志江,梁旭黎,王华明,王德亮.施工期钻井井壁混凝土应变实测分析[J].煤炭学报,2011,36(9):1463-1468.
作者姓名:杨志江  梁旭黎  王华明  王德亮
作者单位:1.中国矿业大学 深部岩土力学与地下工程国家重点实验室,江苏 徐州 221008; 2.中国矿业大学 力学与建筑工程学院,江苏 徐州 221008
摘    要:介绍了温家庄铁矿副井钻井井壁施工期间井壁混凝土应变光纤光栅实测方案,分析了混凝土应变变化规律,结果表明:施工期井壁混凝土以受压为主,环向应变大于竖向应变,应变变化阶段与施工工序相对应。漂浮下沉阶段混凝土应变呈现“双线性”特点,实测应变与导出公式计算值相吻合;增加配重水阶段环向压应变减小而竖向压应变略有增加;首次注浆阶段压应变显著减小,个别出现拉应变;后3次注浆阶段压应变先增加后减小,环向应变变化大于竖向应变;抽排配重水阶段环向压应变显著增加,竖向应变变化不大;二次补注浆阶段压应变先增加后减小,但幅度较前述注浆时有所减小。

关 键 词:钻井井壁  立井  混凝土  应变  
收稿时间:2010-11-03

In-situ measurement and analysis of drilling shaft lining concrete strain during sinking
YANG Zhi-jiang,LIANG Xu-li,WANG Hua-ming,WANG De-liang.In-situ measurement and analysis of drilling shaft lining concrete strain during sinking[J].Journal of China Coal Society,2011,36(9):1463-1468.
Authors:YANG Zhi-jiang    LIANG Xu-li  WANG Hua-ming  WANG De-liang
Affiliation:YANG Zhi-jiang1,2,LIANG Xu-li3,WANG Hua-ming4,WANG De-liang4(1.State Key Laboratory for Geomechanics and Deep Underground Engineering,China University of Mining & Technology,Xuzhou 221008,China,2.School of Mechanics & Civil Engineering,3.Engineering College,Shijiazhuang University of Economics,Shijiazhuang 050031,4.Hebei Research Institute of Construction and Geotechnical Investigation Co.,Ltd.,China)
Abstract:The scheme based on the Fiber Bragg Grating(FBG) for measuring the concrete strains of the drilling shaft lining during sinking of Wenjiazhuang Iron Ore Mine auxiliary shaft was introduced,and the variation of the measured strains was discussed.The results show that the concrete bear compressive strain during drilling sinking,the tangent compressive strain is greater than the vertical and the strain variation phases is corresponding to the sinking phases.In the floating and dropping phase the strain curves ...
Keywords:drilling shaft lining  vertical shaft  concrete  strain  
本文献已被 CNKI 等数据库收录!
点击此处可从《煤炭学报》浏览原始摘要信息
点击此处可从《煤炭学报》下载全文