兰陵新天地深基坑工程设计施工
作者单位:武汉市勘测设计研究院
摘    要:结合兰陵新天地1号楼深基坑工程实例,详细介绍了兰陵新天地1号楼的周边环境、地质条件及基坑支护设计与施工情况。该基坑采用钻孔灌注桩桩排加钢筋混凝土支撑的支护体系与深层搅拌桩和高压旋喷桩的止水帷幕、坑内中深井降水的地下水联合处理方案。监测资料验证了该基坑工程设计、施工的成功。

关 键 词:钻孔灌注桩  止水帷幕  降水井

Design and Construction of Deep Foundation Engineering in Lanling Xintiandi Project
Authors:Shi Mujun  Deng Yilong  Chen Xing
Abstract:The surrounding environment,geological conditions, the design and construction of foundation support in Lanling Xintiandi are introduced in detail.This foundation applies bored pile and reinforced concrete support as support system,and adopts the combining treatment scheme for groundwater which includes waterproof curtain of deep mixing pile and high-pressure jet grouting pile,and deep well dewatering.The design and construction are testified successfully through monitoring data.
Keywords:bored pile  waterproof curtain  dewatering well