摘    要:禹门口黄河提水工程一级泵站厂房施工时,临河侧有10m高的岩坎及位于其上4m高的混凝土档墙形成的围堰。文中介绍了围堰拆除时的爆破施工技术方法、施工质量控制及采取的施工安全措施。

关 键 词:提水工程 泵站 围堰 拆除 爆破施工 施工安全
文章编号:1006-8139(2003)02-65-02
修稿时间:2003-01-20

Blasting Construction of Cofferdam Removal in Yumenkou Pump Station No. 1
Wang Youzhen. Blasting Construction of Cofferdam Removal in Yumenkou Pump Station No. 1[J]. Shanxi Hydrotechnics, 2003, 0(2): 65-66
Authors:Wang Youzhen
Affiliation:Wang Youzhen
Abstract:A line of rock ridge,ten meters high with a concrete retaining wall,four meters high placed on it,along and close by the Yellow River's left bank forming a cofferdam at the time when the construction of Yumenkou pump station No.1's building was being carried out.When the building will be over before long,the cofferdam was to be removed by blasting.In this paper,the construction technique,the quality control in the construction of the blasting for the cofferdam removal are introduced,together with the safety measures which had been taken.