拔贡水电站导水机构拼装
引用本文:李海.拔贡水电站导水机构拼装[J].红水河,2013(6):77-79.
作者姓名:李海
作者单位:广西水电工程局电力安装公司,广西南宁530219
摘    要:拔贡水电站水轮发电机组导水机构尺寸大、重量大、安装调整精度要求高、安装时间短,因此导水机构拼装采用内配水环吊装位置的改变和导叶Y型密封圈的安装时机等方法,实现了在短工期内完成导水机构拼装。

关 键 词:导水机构  导叶  控制环  拔贡水电站

Assembly of Distributor for Bagong Hydropower Station
LI Hai.Assembly of Distributor for Bagong Hydropower Station[J].Hongshui River,2013(6):77-79.
Authors:LI Hai
Affiliation:LI Hai (Electric Power Installation Company of Guangxi Hydroelectric Construction Bureau, Nanning, Gnangxi, 530219)
Abstract:Bagong hydropower station adopts a large and heavy distributor, whose assembly requires high precision and short duration. Therefore, the assembly of distributor is completed in a short period by changing the hoisting posi- tion of the inner water distributing ring and installing the wicket gate's Y-type sealing ring at the right time.
Keywords:distributor  wicket gate  gate operating ring  Bagong Hydropower Station