长沙地区配电网接地方式现状及改造 |
| |
作者单位: | 东营市政工程设计院 山东东营257000(周永明),泮头水库管理所 湖南郴州423000(彭东飞),长沙电业局 湖南长沙410076(刘柯) |
| |
摘 要: | 分析长沙地区10 kV配电网现有的中性点经消弧线圈接地方式及现有的接地方式存在的弊端,提出改造方案:在长沙重负荷的城区将消弧线圈接地方式改造为中性点经小电阻接地方式,在城乡结合部仍保留现有的中性点经消弧线圈接地方式.
|
关 键 词: | 10kV配电网 接地方式 消弧线圈 小电阻接地方式 |
Status and conversion of neutral grounding model in distribution network in Changsha |
| |
Authors: | ZHOU Yong-ming PENG Dong-fei LIU Ke |
| |
Affiliation: | ZHOU Yong-ming1,PENG Dong-fei2,LIU Ke3 |
| |
Abstract: | This paper analyzed the neural grounding system with perterson coil in 10 kV distribution network in Changsha.The shortcomings of existing neural grounding system are analyzed,and the retrofitting scheme of the grounded system for 10 kV distribution networks in Changsha is proposed.The heavy loaded substations near to load center are to be retrofitted to ground with small resistance,and the suburb substation will be reserved unchanged. |
| |
Keywords: | 10 kV distribution network grounded model arc suppression coil grounding via resistance |