小湾水电站电力市场和输电方案概述
引用本文:杨家兴.小湾水电站电力市场和输电方案概述[J].水力发电,2004,30(10):19-20.
作者姓名:杨家兴
作者单位:云南华能澜沧江水电有限公司,云南,昆明,650011
摘    要:根据电力消纳研究,小湾水电站既是满足云南电网负荷发展需要,调整云南电网电源结构的关键性电站,又是优化南方区域能源配置,实施西电东送的主力电源。技术经济比较的结果认为,小湾水电站宜采用直流送电广东,同时以500kV交流接入云南主网,以满足云南负荷需求。

关 键 词:电力市场  电力消纳  输电方案  小湾水电站
文章编号:0559-9342(2004)10-0019-02

Brief introduction to the power market and power transmission scheme for Xiaowan Hydropower Station
Yang Jia-xing.Brief introduction to the power market and power transmission scheme for Xiaowan Hydropower Station[J].Water Power,2004,30(10):19-20.
Authors:Yang Jia-xing
Abstract:According to the electricity consumption analysis, Xiaowan Hydropower Station will be not only a key power plant to meet the increasing power demands and to adjust the power sources structure in Yunnan Power Grid, but also the main power source to optimize energy source disposition in the south part of the country and to implement the program of delivering power from the west to the east. The technical and economic analysis indicated that the power generated from Xiaowan Hydropower Station is preferable to be transmitted to Guangdong Province by DC system and to connect with Yunnan key power grid by 500 kV AC system so as to meet the load demands in Yunnan province.
Keywords:power market  power consumption  power transmission scheme  Xiaowan Hydropower Station