试论建材大幅涨价造成的合同履行障碍
引用本文:郭宝辉.试论建材大幅涨价造成的合同履行障碍[J].山东电力高等专科学校学报,2005,8(4):105-107,66.
作者姓名:郭宝辉
作者单位:山东电力建设第一工程公司,济南,250100
摘    要:2002年以来,钢材、水泥、沙子等主要建材价格大幅度上涨,使建设工程固定总价合同的履行产生了严重障碍。本文论述了关于固定总价合同,在合同履行期间遇到建材大幅上涨,如严格按照原合同履行会使当事人之间的利益显失公平,应当按照情势变更原则变更合同,调整合同价款以平衡当事人之间的利益。

关 键 词:建材大幅涨价  情势变更  变更合同  增加价款

A discussion on hard implementation of fixed lump sum construction contract duet to material price fluctuation
Guo BaoHui.A discussion on hard implementation of fixed lump sum construction contract duet to material price fluctuation[J].Journal of Shandong College of Electric Power,2005,8(4):105-107,66.
Authors:Guo BaoHui
Abstract:In recent years, especially after 2002, the implementation of fixed lump sum contract is facing a critical obstacle due to the hike of main construction materials such as steel, cement, sand,etc. It is considered in this article, it is unfair to two the contract without any parties to execute changes when the material hiked during the implementation of the contract, it should invoke the principle of variation to adjust the contract price to make a benefit balance between two oarties.
Keywords:Hike of Construction Material  Variation  Change of Contract  Increase of Contract Price