长输管路水锤压升的浅析
引用本文:葛旭星. 长输管路水锤压升的浅析[J]. 广东化工, 2013, 0(23): 145-146,128
作者姓名:葛旭星
作者单位:中国天辰工程公司上海分公司,上海200233
摘    要:文章通过管道上阀门开、闭的工况说明水锤产生的原因,从水锤产生的四个阶段逐步分析,确立对于长输管路的水锤的初步计算,同时就现行项目中的苯乙烯长输管路的案例进行了初步的计算及分析,从而从工艺角度提出初步解决或预防方案.

关 键 词:长输管道  切断阀的关闭时间  Joukowsky压升

The Preliminary Analysis of Water Hammer Pressure Increase in the Long Distance Pipeline
Ge Xuxing. The Preliminary Analysis of Water Hammer Pressure Increase in the Long Distance Pipeline[J]. Guangdong Chemical Industry, 2013, 0(23): 145-146,128
Authors:Ge Xuxing
Affiliation:Ge Xuxing (Shanghai Branch Company China Tianchen Engineering Corporation, Shanghai 200233, China)
Abstract:The paper described the cause of the water hammer by analyzing the working condition when the shutoff valve on and off, analyzed the four phases of water hammer step by step, established the preliminary calculation of the long distance pipeline and calculated the water hammer pressure increase lbr the long distant pipeline of styrene in the existed project, then proposed the solution or preventative actions for the water hammer.
Keywords:the long distance pipeline~ the close time ofshutoffvalve  Joukowsky pressure increase