900t铁路大型箱梁双层存放工艺
引用本文:虞巍巍. 900t铁路大型箱梁双层存放工艺[J]. 福建建筑, 2010, 0(4): 117-120,116
作者姓名:虞巍巍
作者单位:中交一公局厦门工程有限公司,361021
摘    要:桥梁下部构造的施工滞后,造成箱梁无法运出架设,为保证梁场的正常生产,采取双层存梁,可以确保箱梁的正常预制,并充分利用梁场的生产设施及人员。本文结合苏州梁场实际施工情况就双层存梁工艺原理、流程及质量控制等多个方面进行阐述。

关 键 词:900t  大型箱梁  双层存放

900t large box girder double of aiiway layer storage technology
Yu Weiwei. 900t large box girder double of aiiway layer storage technology[J]. Fujian Architecture & Construction, 2010, 0(4): 117-120,116
Authors:Yu Weiwei
Affiliation:Yu Weiwei (China communications construction company first highway engineering Company Limited xiamen Engineering Co. Ltd 361021)
Abstract:The construction delay of bridge infrastructure will cause that the box girder can not be carried out of the erection. In order to ensure the regular production in the box beam prefabricated factory, double layer storage beam can be used, which ensures the box girder's regular prefabrication and makes the best of the production facility and personnel. Combining with the practical construction situation in Suzhou box beam prefabricated factory, the process principle, flowsheet and quality control of the double layer storage beam are illustrated in this worko
Keywords:900t large box girder double layer storage