特高拱坝接缝灌浆施工技术与智能建造分析反馈
引用本文:阿旺加措,王克祥,罗贯军,刘春风,杨小龙,龚攀.特高拱坝接缝灌浆施工技术与智能建造分析反馈[J].湖北水力发电,2021,35(1):16-23.
作者姓名:阿旺加措  王克祥  罗贯军  刘春风  杨小龙  龚攀
作者单位:西藏大学理学院,西藏 拉萨 850000;三峡集团西藏能源投资有限公司,西藏 拉萨 850000;中国三峡建设管理有限公司,四川 成都 610041;中国三峡建设管理有限公司,四川 成都 610041
摘    要:白鹤滩工程大坝为300 m级特高双曲拱坝,全坝共30条横缝31层灌区.为确保高质量实施大坝接缝灌浆,充分利用大坝智能温控与智能建造数据分析反馈混凝土梯级降温方式,设计合适温度梯度、混凝土龄期、横缝开张度、悬臂高度等,确定混凝土接缝灌浆的各项条件,从而判断最优灌浆时机,制定接缝灌浆系统安装标准化工艺,充分做好各项灌前准备...

关 键 词:白鹤滩  双曲拱坝  智能反馈  接缝施工

Joint Grouting Construction Technology and Intelligent Construction Analysis and Feedback of Super-high Arch Dam
NGAWANG Gyatso,WANG Kexiang,LUO Guanjun,LIU Chunfeng,YANG Xiaolong,GONG Pan.Joint Grouting Construction Technology and Intelligent Construction Analysis and Feedback of Super-high Arch Dam[J].Hubei Water Power,2021,35(1):16-23.
Authors:NGAWANG Gyatso  WANG Kexiang  LUO Guanjun  LIU Chunfeng  YANG Xiaolong  GONG Pan
Affiliation:(College of Science, Tibet University, Lhasa 850000, China;Tibet Energy Investment Co., Ltd., China Three Gorges Corporation, Lhasa 850000, China;China Three Gorge Construction Management Co., Ltd., Chengdu 610041, China)
Abstract:The dam in Baihetan Project is a 300 m level super-high double-curved arch dam with 30 transverse joints and 31 grouting layers.In order to ensure a high-quality dam joint grouting construction,intelligent temperature control and intelligent construction data analysis and feedback technologies are adopted to determine the cascade cooling schemes of concrete with appropriate parameters such as the temperature gradient,concrete age,transverse joint opening,and cantilever height.Various conditions of the joint grouting construction and thus the optimal grouting timing are determined.Then,standardized installation process of the joint grouting system is formulated,and all pre-grouting preparation work is done thoroughly.Thus,the grout is ensured to evenly and fully fill the concrete joints during the grouting process.Inspection after the grouting construction in Baihetan Project shows that all parameters of the joint grouting process exceed the design requirements and the grouting construction is a high-quality work.
Keywords:Baihetan Project  double-curved arch dam  intelligent feedback  joint construction