首页 | 本学科首页   官方微博 | 高级检索  
     

求解资源受限项目调度问题的改进布谷鸟搜索算法
引用本文:聂慧,刘波,韦向远,杨辉华. 求解资源受限项目调度问题的改进布谷鸟搜索算法[J]. 桂林工学院学报, 2013, 0(3): 529-536
作者姓名:聂慧  刘波  韦向远  杨辉华
作者单位:[1]中国矿业大学(北京)力学与建筑工程学院,北京100084 [2]桂林电子科技大学人事处,广西桂林541004 [3]桂林电子科技大学广西信息科学实验中心,广西桂林541004
基金项目:国家自然科学基金项目(61163058,21365008);国家科技部重点科技开发项目(2012BAK24B0201);广西软科学研究项目(桂科软11217002-32)
摘    要:针对资源受限项目调度问题(RCPSP),提出一种基于改进布谷鸟搜索(ICS)算法的高效求解方法.ICS算法设计如下:在解空间表示方面提出一种适应莱维飞行特点的任务调度顺序优先级编码方案,并采用串行调度求解该问题;为提高算法收敛速度、避免陷入局部最优解,对CS的局部搜索机制进行改进,即引入对精英个体的局部搜索策略及对首领的寿命衰老机制.最后,通过PSPLIB基准测试问题J30、J60和J90对算法性能进行测试,并与CPLEX优化结果及参考值进行比较,结果表明ICS算法较CS算法收敛更快、结果更优,调度结果理想.

关 键 词:资源受限项目调度问题  布谷鸟搜索算法  精英个体局部搜索  寿命衰老机制

Improved Cuckoo Search Algorithm for Resource-Constrained Project Scheduling
NIE HuiTM,LIU Bo,WEI Xiang-yuan,b,YANG Hui-hua. Improved Cuckoo Search Algorithm for Resource-Constrained Project Scheduling[J]. Journal of Guilin University of Technology, 2013, 0(3): 529-536
Authors:NIE HuiTM  LIU Bo  WEI Xiang-yuan  b  YANG Hui-hua
Affiliation:2b (1. School of Mechanics and Civil Engineering, China University of Mining and Technology (Beijng), Beijing 100084, China ; 2. a. Personnel Department ; b. Guangxi Experiment Center of Information Science, Guilin Uni- versity of Electronic Technology, Guilin 541004, China)
Abstract:An efficient Improved Cuckoo Search (ICS) algorithm is proposed to solve the resource-constrained project scheduling problem (RCPSP). The improved CS algorithm is designed as follows, each individual is coded based on the priority of task for scheduling as to be in a form suitable for matching the characteristics of Lrvy flights, and then this individual should be resolved by serial scheduling method. To avoid low efficiency and local minimum, both an elite individual local search method and a mechanism of aging are introduced in the local search phase of CS in addition. To validate the efficiency of ICS, both CS and ICS algorithms are tested on RCPSP of J30, J60 and J90 taken from PSPLIB benchmark. The results are compared with reference values and the optimum results by CPLEX. The results show that ICS always has faster convergence speed and shorter makespan than CS. The approach provides an efficient method for solving other scheduling and optimization problems.
Keywords:resource-constrained project scheduling problem  cuckoo search algorithm  elite individual localsearch  mechanism of aging
本文献已被 维普 等数据库收录!