Abstract: | 1. |
The design scheme of the 500-kV OEE of the Sayano-Shushenskoe hydrostation has a number of substantial shortcomings reducing the reliability of power output. Reconstruction of the middle network of the existing 4/3 scheme to three networks with two switches per connection is the most optimal variant of reconstruction. Sectioning of the collecting bus systems is necessary for a further increase of the reliability of the scheme.
| 2. |
In the case of repair works on equipment of small nonstandard switchgear, such as the 500-kV OEE of the Sayano-Shushenskoe hydrostation, it is necessary to use special equipment and mechanisms, the development of which must be recommended to domestic industry.
|
Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 4, pp. 37–39, April, 1994. |