首页 | 本学科首页   官方微博 | 高级检索  
     

象鼻岭水电站引水发电系统开挖工程的安全管理
引用本文:金海斌.象鼻岭水电站引水发电系统开挖工程的安全管理[J].山西建筑,2014(27):273-274.
作者姓名:金海斌
作者单位:中国葛洲坝集团六公司
摘    要:针对象鼻岭水电站引水发电系统开挖工程地质条件复杂、洞室密集、稳定性差的特点,分析了安全管理的重点和难点,通过安全策划,确立了该工程的安全管理方法,并作了一一阐述,实现了安全管理零伤亡的目标。

关 键 词:安全管理  水电站  危险  制度

The safety management of Elephant Trunk Hill Hydropower Station diversion power generation system excavation engineering
JIN Hai-bin.The safety management of Elephant Trunk Hill Hydropower Station diversion power generation system excavation engineering[J].Shanxi Architecture,2014(27):273-274.
Authors:JIN Hai-bin
Affiliation:JIN Hai-bin(The Sixth Company, China Gezhouba Group, Zhaotong 657000, China)
Abstract:According to the characteristics of complex geological condition,dense cavities,poor stability of Elephant Trunk Hill Hydropower Sta-tion diversion power generation system excavation engineering,this paper analyzed the emphases and difficulties of safety management,through the safety planning,established the safety management method of the project,and made elaboration one by one,gained the safety management objectives of zero casualties.
Keywords:safety management  hydropower station  risk  system