怀化石煤电厂接入系统方案研究
引用本文:王振宇,凌骏,苏志扬. 怀化石煤电厂接入系统方案研究[J]. 华中电力, 2010, 23(1): 19-22
作者姓名:王振宇  凌骏  苏志扬
作者单位:湖南省电力勘测设计院,湖南长沙,410007
摘    要:为满足湘西地区用电需求并缓解湘南受端系统的供电压力,怀化石煤发电工程将在2012年建成投产。研究表明,怀化石煤发电工程通过剖进艳山红-宗元500kV线路接入系统是适宜的。

关 键 词:怀化石煤电厂  接入系统方案  潮流迂回  安全稳定  综合年费用

Study on Scheme of Connecting Huaihua Stone-coal Power Plant to Hunan Power Grid
WANG Zhen-yu,LING Jun and SU Zhi-yang. Study on Scheme of Connecting Huaihua Stone-coal Power Plant to Hunan Power Grid[J]. Central China Electric Power, 2010, 23(1): 19-22
Authors:WANG Zhen-yu  LING Jun  SU Zhi-yang
Affiliation:Hunan Electirc Power Design Institute;Changsha 410007;China
Abstract:To meet the load demand of Xiangxi district and alleviate the supply pressure of Xiangnan power grid,Huaihua Stone-coal power plant is to be up and running in 2012.The study concludes that it is adaptable for Huaihua Stone-coal power plant to connect the Hunan power grid cutting through Yanshanhong-Zongyuan 500kV transmission lines.
Keywords:huaihua stone-coal power plant  connection to the grid  load by pass  security and stability  overall annual cost  