基于五花山水库导流方案优化
引用本文:范丽君 孙 飚. 基于五花山水库导流方案优化[J]. 黑龙江水利科技, 2013, 0(11): 39-40
作者姓名:范丽君 孙 飚
作者单位:[1]黑龙江省水利工程建设局,哈尔滨150081 [2]黑龙江省水利水电勘测设计研究院,哈尔滨150080
摘    要:五花山水库是一座以城镇供水为主,兼顾发电、森林防火及改善生态环境的中型水库工程。工程于2010年开工,针对初设推荐的施工导流方案施工复杂而且工程量大,总工期长问题,在参建各方共同商讨下,进行了优化。将明渠布置到左岸,一期施工右岸,二期填筑明渠缺15。明渠段坝体基础帷幕灌浆和混凝土防渗墙可以在第一年明渠施工期间完成,节省时间,减少导流工程量和投资。五花山水库工程按以上综合优化后的方案进行施工布置,施工总工期由36个月缩短至28个月,为工程节省了投资,缩短了工期。

关 键 词:五花山水库  导流方案  优化  缩短工期  节省投资

Reservoir Diversion Scheme Optimization for Wuhuashan Reservoir
FAN Li-jun and SUN Biao. Reservoir Diversion Scheme Optimization for Wuhuashan Reservoir[J]. Heilongjiang Science and Technology of Water Conservancy, 2013, 0(11): 39-40
Authors:FAN Li-jun and SUN Biao
Affiliation:FAN Li-jun and SUN Biao (1. Heilongjiang Province Hydraulic Engineering Construction Bureau, Harbin 150081, China; 2. Heilongjiang Province Water Conservancy & Hydropower Investigation, Design and Research Institute, Harbin 150080, China)
Abstract:Wuhuashan reservoir is a medium-sized reservoir mainly for water supply, giving consideration to generation ,forest fire prevention and the improvement of the ecological environment. The construction was launched in 2010, according to preliminary design recommended construction diversion scheme is complex and large quantities, the long construction period problem, diversion scheme was optimized under the discussion of participation of all parties. The open channel was disposed to the left bank, the first period of construction was conducted on the right bank, the second period channel gap filling. Open channel section of dam foundation curtain grouting and concrete anti-seepage wall can be completed during the first year of channel construction, saving a lot of time, the diversion engineering quantity and investment were reduced. Finally, by adopting above scheme the total construction period was shortened from 36 months to 28 months, saving cost and shortening the construction period.
Keywords:Wuhuashan reservoir  diversion scheme  optimization  shortening construction period  saving cost